Monday, May 20, 2013

Kitchen Remodel

I recently got my kitchen remodeled in an effort to get my condo ready to sell. I wanted to take this as an opportunity to talk about my experience. This whole experience is so topical to class that it’s shocking.
My goal was to get the kitchen in “good enough” shape to sell since it was the room that needed the biggest improvement. I suspect this will aid in getting a better sale price, we’ll see soon enough. I initially budgeted $5000 for the remodel, which included refinishing most of the cabinets, the floor and putting it a countertop that was a little higher quality than the existing one.

I hired a guy to do all this, and while he didn’t provide me with a concrete estimate (mistake #1), he was confident that the work and budget were reasonable. We also agreed that the job would take 2-3 weeks, again given the assurance that this may not be exact, but it is reasonable. The deal was that I pay for materials and labor at an hourly rate. He’s not an experienced contractor, but I don’t mind working with a guy trying to get started and help out a local.

Ultimately, the job took about 6 weeks and over $9000. Ouch! While that’s certainly not ideal, it’s interesting looking back what I should’ve done differently. I haven’t worked with a ton of contractors directly, so I might have unrealistic expectations on what they will agree to. However, my experience with the contractor that remodeled my bathroom was far better in this respect, and I think I pinpointed three interdependent reasons why.

Risk Ownership

One issue that didn’t occur to me when agreeing to the flat hourly rate was that I owned all the risk. I don’t expect the contractor to assume all the risk either, but any delay to the work, any problems, and changes to the plan (even a non-existent one) fall on me. In retrospect, this is wasn’t a wise move. One reason for that is that it’s extremely unlikely to reap the rewards of this risk. Are there really any serious expectations that a job like this will go significantly under budget? Yeah, right.

In class, as we keep going through valuation of business and risk analysis, generally everyone is looking to at least balance risk and reward, if not find opportunities with high reward for low risk (a feat that if I could do reliably would negate the need for school, and I’d currently be having a beer with Warren Buffet).

So, given a chance to redo this remodel, I’d probably insist on some way to mitigate the risk ownership. On the previous remodel, I’m sure I paid for labor somewhat directly (it isn’t clear from his invoice), but this was also never discussed. We agreed on a budget and work to be done and it was done. So, either everything stayed on schedule and I didn’t notice that I paid direct labor or he was just charging me for the work and assuming all the risk on his own. Unfortunately, I just don’t have enough data to know what a reasonable labor payment scheme that shares the risk appropriately would be.

Estimation

Next, we never agreed on a clear estimation of the work required. He had concerns about how much time the cabinet refinishing would take. Aside from that, I never got a clear estimation on how much and how long this would actually take. This ties to the risk ownership in that I agreed to the job with no estimation and all the risk.

We’ve been working a lot on valuation, which definitely requires some reasonable expectations. I’m curious to see how this goes in practice. It seems incredibly difficult, and everyone says that you end up throwing out the plan on day one anyway. As Mike Tyson has said, “everyone has a plan until they get punched in the mouth.”

We ended up never even trying to estimate the job in any formal sense. In retrospect, even with some serious unknowns, I wish I had written down some estimates, it would have naturally created triggers when the estimates were off. Which leads to…

Measurement

Throughout the weeks of work, I’d ask, “how we doin?” and get a response, “alright, some minor hiccups but we’re making progress.” Sounds good, now that that’s under control, time to get back to accounting homework, right? Well, lesson learned. Had I actually been tracking the labor hours along the way, I wouldn’t have been shocked by it at the end. Near the end of the project, he gives me all his worked hours, and I about spewed tea all over the place. When I was at around the budget of the project, it was roughly half done! The huge shock of this was not a welcome surprise.

In the end, I was a horrible manager. I was in charge, I had the ability to collect the necessary data, and I decided to work on homework instead. Lesson learned, homework is never the answer. With tongue removed from cheek, I do have to admit this was a valuable learning experience on setting expectations, measuring progress and dealing with some difficult conversations.